The Chinese New Year factory shutdown begins on 6 February 2027, but the holiday is not the shutdown. Chinese factories lose four to six weeks of usable capacity around Spring Festival, while the public holiday itself runs eight days. Orders that must ship before the break need to be placed between October and early November 2026.
In this guide
- The short answer to the Chinese New Year factory shutdown in 2027
- Official holiday versus real shutdown
- The 2027 double shutdown: Spring Festival meets Ramadan
- Working backwards from the Chinese New Year factory shutdown
- What changes factory by factory
- The three windows SourceEyes plans around
- A known shutdown is not force majeure
- Key takeaways
- Where SourceEyes helps
- Frequently asked questions
The short answer to the Chinese New Year factory shutdown in 2027
Here is what the Chinese New Year factory shutdown does to a 2027 order:
| 2027 date | |
|---|---|
| New Year’s Eve | Friday 5 February |
| Lunar New Year’s Day | Saturday 6 February |
| Public holiday, under the 2024 rules | at least 8 days |
| Ramadan begins | Monday 8 February |
| Lantern Festival | Saturday 20 February |
| Order cut-off, custom and project goods | 9 October – 8 November 2026 |
| Pre-shipment inspection deadline | mid-January 2027 |
Count backwards from 5 February 2027 using your own production lead time, then add a two-to-three-week buffer. That arithmetic, not the holiday dates, is what the Chinese New Year factory shutdown really costs: the difference between a February shipment and a March one.
Official holiday versus real shutdown
The gap between the calendar and the factory floor is the most expensive misunderstanding in any Chinese New Year factory shutdown. China’s statutory Spring Festival holiday is four days: New Year’s Eve plus the first three days of the lunar year. The annual holiday schedule published by the State Council stretches that to a minimum of eight days by adjusting working weekends.
The 2024 revision of the national holiday rules adds a detail that matters here: when New Year’s Eve falls on a Friday, the break can run to nine days, and the revision names 2027 as the example. The specific 2027 schedule has not been published yet, and it normally arrives in November of the preceding year.
Factories, though, do not run to the government calendar. They run to chunyun, the 40-day travel rush around Spring Festival. The Ministry of Transport counted 9.41 billion inter-regional trips during the 2026 chunyun, with a single-day peak of 380 million. Most production workers travel home across provinces, and they leave up to a week before the official holiday and return a week or more after it.
| Phase | Typical duration |
|---|---|
| Statutory Spring Festival holiday | 4 days |
| Official schedule with adjusted weekends | 8–9 days |
| Factory closure, furniture and project goods | 2–4 weeks |
| Capacity booked out before the break | final 1–2 weeks |
| Output back to normal after reopening | 1–2 weeks |
| Effective planning gap | 4–6 weeks |
A portion of the workforce changes employer over the holiday, so the first weeks after reopening are spent rehiring and retraining before lines run at full speed. Upstream suppliers close on the same calendar, which is why a workshop that reopens promptly can still sit idle waiting for hardware, coatings, foam, glass or packaging. This is the engine of the Chinese New Year factory shutdown: not one closed week, but a supply chain that stops and restarts in sequence.
SourceEyes plans a Chinese New Year order around three dates rather than one holiday: the last inspection date, the last loading date and the restart date. Everything before the break is worked back from the 6 February 2027 holiday start.
Freight moves on the same calendar, and it is worth separating what SourceEyes controls from what it does not during a Chinese New Year factory shutdown. Spot rates and sailing schedules both tighten in the four weeks before the closure, and the cost of shipping from China is your forwarder’s number rather than ours. Booking early protects your schedule. The SourceEyes part of the chain ends when the goods are on board.
The 2027 double shutdown: Spring Festival meets Ramadan
Ramadan begins on Monday 8 February 2027 — three days after New Year’s Eve — and Eid al-Fitr falls around 10 March. Chinese factories are down, and buyers in the Gulf, Southeast Asia and North Africa are simultaneously in their slowest decision month of the year: shorter working days, and purchasing approvals that routinely slip to after Eid.
That overlap changes the shape of the Chinese New Year factory shutdown for these markets. It is not only that goods cannot be produced in February. It is that the approval that would have triggered production arrives late as well. Anything that needs a signed order, an approved sample or a deposit before production can start has to clear before Ramadan begins, or it waits until mid-March.
Two consequences follow for the 2027 Chinese New Year factory shutdown, and both are planning problems rather than information problems: samples approved in December give a factory a workable window in January, while samples approved in January usually mean a March order. And the deposit is what holds a slot, not the conversation.
SourceEyes runs two checks before your goods move on a Chinese New Year order: your supplier’s stop and restart dates are confirmed in writing, and the inspection is booked before mid-January 2027. Both sit on the delivery date you agreed, so a slip appears while there is still time to react.
Working backwards from the Chinese New Year factory shutdown
These are the dates SourceEyes plans around when a client wants goods on board before the Chinese New Year factory shutdown. They assume samples and specifications are already approved.
| Your order | Production | Place the order by | Inspect by |
|---|---|---|---|
| Custom joinery, doors, windows, stone, FF&E | 30–60 days | 9 Oct – 8 Nov 2026 | mid-January 2027 |
| Ceramics, tiles, sanitaryware, building materials | 30–45 days | late Oct – mid Nov 2026 | mid-January 2027 |
| Standard products, sea freight, 30-day lead time | 30 days | November 2026 | mid-January 2027 |
| Small volumes, air freight | under 30 days | late November – December 2026 | before the closure |
The reason those cut-offs sit in autumn is not the holiday itself — it is the queue in front of it. In the last one to two weeks before closure, production slots at most factories are effectively gone, and anything not already on the line becomes a March order regardless of what the theoretical lead time says.
One calendar trap is worth naming in the 2027 Chinese New Year factory shutdown. The 140th Canton Fair runs 15 October to 4 November 2026 — inside the same window in which custom orders have to be locked in. Buyers who fly out to meet suppliers in late October are often deciding at exactly the point where the pre-holiday capacity has already been allocated.
What changes factory by factory
The length of a Chinese New Year factory shutdown is not a national number. It follows the workforce and the equipment.
- Electronics and assembly in the Pearl River Delta. Production workers are drawn from provinces several hours away by rail, so departures start earlier and returns are staggered. Lines restart gradually rather than all at once.
- Textiles, hardware and machinery in the Yangtze River Delta. More of the workforce comes from within the region, where the trip home is measured in hours. Restart sits closer to the official reopening date.
- Ceramics, glass and anything with a kiln. A kiln is not switched off like a light. It is cooled over days and fired back up over days, so a plant that looks open may not yet be producing. These are typically the first to stop and among the last to reach full output.
- Upstream suppliers of every category. Hardware, coatings, foam, glass, fabric and packaging all close on the same calendar, so a late-opening assembly line waits for parts anyway.
Treat these as planning bands rather than promises from any individual factory. The useful move when planning a Chinese New Year factory shutdown is to ask your supplier for their own dates in writing, including their last production day and their restart day, and to plan against the later of the two rather than against the official holiday. Choosing a factory on its restart discipline, and not only on its price, pays for itself once a year.

The three windows SourceEyes plans around
Working the China side, SourceEyes reduces the Chinese New Year factory shutdown to three dates on a calendar: the last day an inspection can be booked, the last day goods can be loaded, and the first day production restarts.
The inspection window. Third-party inspection capacity disappears with the holiday, and inspection slots fill first at exactly the moment everyone wants them. Pre-shipment inspection for an order that must ship before the Chinese New Year factory shutdown has to be completed by mid-January 2027. SourceEyes runs inspections against the ISO 2859-1 sampling standard, with photographs matched to the approved sample, and reports against AQL levels agreed before the visit rather than after it.
The loading window. In the final two weeks of the Chinese New Year factory shutdown, finishing, packing and loading are all compressed into fewer working days, and inland trucking thins out as drivers travel home too. Loading supervision belongs in that window, not after it.
The first post-holiday batch. The weeks after reopening carry the highest defect risk of the year: new workers, retrained lines, materials that have been sitting. SourceEyes treats the first batch after the break as a separate inspection point rather than assuming continuity from December.
SourceEyes is a sourcing and QC team based in Suzhou, China, working the China side of a sourcing programme — from finding the right factory to loading your goods on board, which is where the scope ends. Onward freight, destination clearance and delivery sit with your importer or forwarder, and SourceEyes hands over the documents they need.
A known shutdown is not force majeure
Buyers occasionally assume that a missed Chinese New Year factory shutdown deadline sits in the same category as a natural disaster. It usually does not. The ICC Force Majeure Clause turns on whether an event was reasonably foreseeable and outside a party’s control, and Spring Festival is published, annual and predictable. A delivery date that ignores it is a delivery date the buyer agreed to.
The practical implication is that the buffer has to sit inside your own schedule. If a contract promises goods in February and the production window closes in mid-January, no clause rescues the date. The payment and delivery terms you agree are where that buffer has to live. Working backwards from 5 February 2027 and adding the buffer is the whole defence.
Key takeaways
- The 2027 Chinese New Year factory shutdown starts 6 February. New Year’s Eve is Friday 5 February, and the official holiday runs at least eight days.
- Plan for four to six weeks, not one. Two to four weeks of closure plus one to two weeks of ramp-up is the real gap in capacity.
- Custom and project orders must be placed between 9 October and 8 November 2026. Standard sea-freight orders by November; air freight can wait until December.
- Pre-shipment inspection closes in mid-January 2027. Inspection capacity goes with the holiday, and slots fill first.
- Ramadan begins 8 February 2027, three days after New Year’s Eve, which delays decisions in Gulf, Southeast Asian and North African markets by weeks.
- The shutdown is not force majeure. It is foreseeable, so the buffer belongs in your own delivery dates.
- Ask your factory for two dates in writing. Their last production day and their restart day matter more than the official Chinese New Year factory shutdown calendar.
Where SourceEyes helps
SourceEyes works the China half of a sourcing programme from Suzhou, Jiangsu: supplier shortlists and factory audits, production follow-up, price negotiation, and inspection before shipment. On the Chinese New Year factory shutdown, that means confirming your supplier’s own stop and restart dates, booking inspection before mid-January, supervising loading in the last compressed week, and checking the first batch after the restart.
Leown Zhang runs inspections, Quinn Sun handles supplier research and logistics coordination, and Betty Gao takes the commercial side — three core members, plus per-project specialists brought in as a programme needs them. SourceEyes fees are on the pricing page, quoted separately from the factory’s price, and you pay the factory directly. If you are still deciding whether the China side needs a team at all, what a sourcing agent does is the place to start.
If you are planning a 2027 order, tell us the product and the quantity and SourceEyes will work the dates backwards with you — including telling you when the schedule no longer fits. How it works sets out the SourceEyes sequence step by step, the SourceEyes services page covers what sits inside the scope, and the pre-shipment inspection checklist shows what an inspection should include whether or not you work with SourceEyes. Contact us and a real person replies within 24 hours.
Frequently asked questions
When do Chinese factories close for Chinese New Year 2027?
Chinese New Year falls on Saturday 6 February 2027, with New Year’s Eve on Friday 5 February. The official holiday runs at least eight days from New Year’s Eve, but the Chinese New Year factory shutdown in practice is longer at both ends: many factories stop production one to two weeks before the holiday and take one to two weeks to reach full output again.
How long is the Chinese New Year factory shutdown really?
For furniture, ceramics and project goods, plan for a four-to-six-week gap in usable capacity. That is two to four weeks of closure plus one to two weeks of ramp-up as workers return in batches and lines are retrained. The eight-day public holiday is the smallest part of the Chinese New Year factory shutdown.
When should I place my order to ship before Chinese New Year 2027?
Custom and project orders should be placed between 9 October and 8 November 2026. Standard products with a 30-day production lead time should be placed by November 2026. Anything placed in December is realistically a March shipment, because the production slots that close before a Chinese New Year factory shutdown are allocated one to two weeks early.
Can I still book an inspection in January 2027?
Yes, but book it early. Pre-shipment inspection for goods shipping before the break needs to be completed by mid-January 2027, and inspection capacity goes on holiday with the factories. Slots in the final fortnight of the Chinese New Year factory shutdown fill first, and AQL levels should be agreed before the visit rather than after it.
Is Chinese New Year force majeure in a supply contract?
Usually not. Force majeure clauses, such as the ICC’s 2020 clause, generally require an event that was not reasonably foreseeable. Spring Festival is published annually and predictable, so a missed February delivery date is normally a planning failure rather than an excused one. Build the buffer into the delivery date you agree.